What this unit covers

MWA A, Performs common occupational skills, is about 11 of the 100 exam questions: Task A-1 safety-related functions (2), A-2 tools and equipment (2), A-3 organizing work (2), A-4 support components (2), A-5 commissioning and decommissioning (2) and A-6 communication and mentoring (1). These are original, independent practice notes; they are not documents of the Red Seal Program, the CCDA or any provincial authority. Code questions are answered with your own copy of the Canadian Electrical Code 2024, supplied in the exam room; these notes do not reproduce its tables or values.

Protection and hazards

Lockout and test before touch

Tools, access and rigging

Organizing work

Supports and seismic restraint

Commissioning, communication and mentoring

Take the free test · full question bank and mock exams with a subscription

Sample questions (5)

1. An electrician is reviewing how to control a hazard before a job. In the hierarchy of controls, which measure is the last line of defence?

  1. Personal protective equipment that the worker wears
  2. Elimination of the hazard through a change to the job
  3. Engineering controls such as barriers and guards
  4. Administrative controls such as written procedures

PPE is the last line of defence because it does not remove the hazard; it only reduces harm to a worker who is still exposed to it (RSOS sub-task A-1.01). Eliminating the hazard is the first and most effective control, while engineering controls and administrative procedures both rank ahead of PPE.

2. During a pre-use inspection, an electrician finds frayed stitching on the shoulder strap of a full body harness. What must be done with the harness?

  1. Use it for restraint work close to the ground
  2. Tag it as defective and take it out of service
  3. Repair the stitching on site with strong thread
  4. Use it with a second lanyard added as a backup

RSOS sub-task A-1.01 requires faulty PPE to be replaced or tagged and removed from service, and section 26.6 of O. Reg. 213/91 requires a defective fall arrest component to be taken out of service immediately. Section 26.4 of O. Reg. 213/91 applies the same rule to a travel restraint system, a field repair with thread is not a manufacturer repair, and a second lanyard does not make a damaged harness safe.

3. A new cleaning product arrives on site. Under WHMIS 2015, which document gives the detailed hazard, handling and first aid information for the product?

  1. The pictogram printed on the supplier label
  2. The technical data sheet for the product
  3. The safety data sheet for the product
  4. The workplace label on a decanted container

Under WHMIS 2015, the safety data sheet (SDS) carries the detailed hazard, handling, storage and first aid information for a hazardous product (RSOS sub-task A-1.02). A pictogram only signals the hazard class, a technical data sheet describes product performance and uses rather than hazards, and a workplace label on a decanted container gives only the product name, safe handling information and a reference to the SDS.

4. A feeder disconnect has been opened, locked and tagged. The electrician will check for absence of voltage with a voltage tester. When must the tester be proven on a known source?

  1. Once, at the start of the shift, before any lockout begins
  2. After the tested conductors have read zero volts
  3. When the tester has been dropped or its battery is low
  4. Immediately before and again after testing the conductors

A tester can fail without warning, so a zero reading means nothing unless the tester is proven on a known live source just before and just after the check (RSOS sub-task A-1.03, test before touch). Proving it once per shift, only after a zero reading, or only after damage leaves a failed tester undetected during the test itself.

5. Two electricians will work at the same time on a motor feeder that is isolated by one disconnect. How must the disconnect be secured?

  1. Each electrician places a personal lock and tag on a multi-lock hasp
  2. The first electrician locks it and the second electrician signs the tag
  3. One lock is applied and its key is shared between the two workers
  4. A tag is installed on the disconnect, because two workers are present

Each worker must control the isolation personally, so every electrician adds an individual lock and tag to a multi-lock hasp (RSOS sub-task A-1.03, group lockout). Relying on another worker's lock, sharing one key, or using a tag alone leaves one worker unprotected; section 190 of O. Reg. 213/91 also requires a means to communicate the status of the lockout when more than one worker is involved.

Start free